GAGREEN WATER SUPPLY PROJECT DISTT JHALAWAR
Project Cost: | Rs 351.48 Cr |
---|---|
Project Status: | Completed |
Project Initiated: | 2013 Year |
Design Year: | 2046 year |
Coverage: |
311 Villages |
Population Benefited: | 519032 (Year 2046) Villages |
Gagreen water supply project for coverage of 311 villages & 36 OH of Jhalawar District was sanctioned in 192th PPC for RS 351.48 Cr. Work order for the project was awarded to M/S SPML Infra Gurgaon on 22.08.2013. Coverage of villages under the project was started from June 2019 and all the villages proposed under the project has been commissioned up to May 2019, in phase manner. Physically project has been completed on 24.09.2021 and since then regular water supply in the connected villages is being done through Public Stand Posts. Presently project is running under O&M by the project executing firm