ATRU SHERGARH WATER SUPPLY PROJECT DISTT BARAN
Project Cost: | 89.69 Cr |
---|---|
Project Status: | Completed |
Project Initiated: | 2016 |
Design Year: | 2049 |
Coverage: |
26 Villages 03 Towns |
Population Benefited: | 107278 (Year 2049) Villages |
Atru Shergarh water supply project for coverage of 03 towns, 26 villages &07 OH of Baran District was sanctioned in 197th PPC for 89.69 Cr. Work order for the project was awarded to M/S Vishnu Prakash R. Punglia Jodhpur on 24.03.2017. Coverage of villages under the project was started from April'2019 and all the villages proposed under the project has been commissioned up to October'2019, in phase manner. Physically project has been completed on 31.01.2020 and since then regular water supply in the connected villages is being done through Public Stand Posts. Presently project is running under O&M by the project executing firm