RWSS RGLC RD 159.150 Km Panchala-Ghewra-Cherai-Project, District Jodhpur
Project Cost: | Rs. 396.63 Cr. |
---|---|
Project Status: | Completed |
Project Initiated: | 2013 |
Design Year: | 2044 |
Coverage: |
59 Villages |
Population Benefited: | 233505 Souls Villages |
· A&F sanction in 190th PPC dated 30.05.13 for Rs Rs.396.63 Cr
· Source- Rajiv Gandhi Lift Canal
· MP Constituency: 5 villages of Jodhpur & 54 villages of Pali Distt.
· MLA Constituency: 54 village of Osian & 5 villages on Lohawat Distt.
· Work order issued by M/s IVRCL, Hyderabad dt. 4.10.13 for Total: Rs. 348.77 Cr. (Rs.320.27 Cr (Execution Part) & Rs.28.50 Cr (O&M Part)
· Stipulated date of commencement: dt. 14.10.2013
· Stipulated date of completion: dt. 14.10.2016
· Benefitted: 59 Main Habitations & 885 Other Habitations
· Project completed : Nov 2021 (Presently under O&M)