Project 5

आरडब्ल्यूएसएस आरजीएलसी आरडी 159.150 किलोमीटर पंचला-घेवरा-चेराई-परियोजना, जिला जोधपुर

Project Cost: Rs. 396.63 Cr.
Project Status: Completed
Project Initiated: 2013
Design Year: 2044
Coverage: 59 Villages
Population Benefited: 233505 Souls Villages

·         A&F sanction in 190th PPC dated 30.05.13 for Rs Rs.396.63 Cr

·         Source- Rajiv Gandhi Lift Canal

·         MP Constituency:  5 villages of  Jodhpur & 54 villages of Pali Distt.

·         MLA Constituency: 54 village of Osian & 5 villages on  Lohawat Distt.

·         Work order issued by M/s IVRCL, Hyderabad dt. 4.10.13 for Total: Rs. 348.77 Cr. (Rs.320.27 Cr  (Execution Part) & Rs.28.50 Cr (O&M Part)

·         Stipulated date of commencement: dt. 14.10.2013

·         Stipulated date of completion: dt. 14.10.2016

·         Benefitted: 59 Main Habitations & 885 Other Habitations

·         Project completed  : Nov 2021 (Presently under O&M)